          LORCAT Processing Setup                               In LORCAT, by scaling the simulated sawing time up or
          The Log Recovery Analysis Tool (LORCAT) 4.0 was configured   down, the sawing times can be adjusted to match a specified
          to simulate the sawing practices of the typical eastern US   annual production volume.
          hardwood sawmill. Table 2 gives an overview of the sawing   This is accomplished by the user specifying in LORCAT

          settings used in the LORCAT simulations conducted.  the hourly production volume. The hourly production volume
            The minimum opening face width was 5.5-inches, with a   is estimated by dividing the annual production volume by
          minimum lumber length of 8-feet. A random-width, 6-inch-tall   the total number of annual operating hours. The analyses
          cant was sawn for all logs, which then was sawn into lumber   specified that the mill operated 2,250 hours per year, based
          using a gang-resaw, as specified in Table 2.       on the average annual production data from NHLA.
            The target thickness for the headrig and the gang-resaw   This equates to approximately 281 operating days per year,
          was calculated using Brown’s equation. LORCAT was instructed   somewhat more than the 250 to 253 working days estimated
          to simulate grade sawing, where the log is rotated and boards   by the production estimates of Hardwood Market Report.
          are sawn from the highest-grade face until a user-specified   Thus, for the annual mill production volumes of 4, 8, and

          cant thickness is achieved.                        12  MMBF,  the  hourly  production  volumes  are  1,778,  3,555,
            It was specified  that  the analyses simulate split-taper   and 5,333 bdft, respectively.
          sawing, where the taper of the log is split between opposite
          faces and the log is sawn parallel to its central axis.  Log, Lumber and Residues Prices
                                                             To perform  an  accurate  costing  analysis that  reflects
          Mill Processing Volume                             current market conditions, accurate and current log and
          Luppold and Bumgardner estimated that the average hardwood   lumber prices are required. Average red oak log prices

          sawmill across all size categories in the Northeastern and   for the first half of 2024 were obtained from the Kentucky
          North Central regions of the US produces approximately four   Division of Forestry.
          million board feet (MMBF) lumber per year. Bergman and Bowe   These reports show delivered log prices to sawmills by
          defined a large hardwood sawmill as one that produces 10   region and by quality: high, medium, and low. Region 4,
          MMBF or more lumber per year.                      Eastern Kentucky, has the most complete data and reported
            These authors also reported that the average large hardwood   the price of red oak logs per thousand board feet Doyle scale
          sawmill produced a mean volume of 15.25 MMBF per year.   as $544, $402, and $133 for high, medium, and low-quality
          Similarly,  Lang reported  that  the  average  hardwood sawmill   logs, respectively.
          produces 14 MMBF per year. However, Lang acknowledges   Rogers states that the high, medium, and low-quality sorts

          that the mills included in their study also produced softwood   are approximately equivalent to the USDA Forest Service Log
          lumber.                                            Grades Factory 1, Factory 2, and Factory 3, respectively.
            NHLA data revealed that the average NHLA member produced   Market prices for green red oak 4/4 thickness lumber in
          approximately 11.75 MMBF of lumber per year. Based on this   the Appalachian region are listed in Table 3 of Hardwood
          information, LORCAT was configured to simulate three mills   Market Report’s weekly pricing report.
          that produced approximately 4, 8, and 12 MMBF per year.  HMR does not report prices for F1F or Selects. Johnson,
            LORCAT uses the log sawing time data collected by Adams   however, states that FAS lumber prices can be used to estimate

          and Adams and Dunmire to estimate the sawing time for   F1F and Selects prices at 0.98 percent and 0.95 percent of
          each log based on log grade, scaling diameter, and length.   the FAS price, respectively.